SlideShare a Scribd company logo
PROJECT MANAGEMENT  ● ENGINEERING  ● CONTRACTING Iv-Oil & Gas www.iv-groep.nl DEVELOPMENT OF A MARGINAL SATTELITE FIELD
PROJECT MANAGEMENT  ● ENGINEERING  ● CONTRACTING INTRODUCTION Iv-Oil & Gas www.iv-groep.nl
PROJECT MANAGEMENT  ● ENGINEERING  ● CONTRACTING INTRODUCTION Wintershall Noordzee BV is investigating the feasibility to utilize a low cost option to develop satellite fields located in the Dutch Sector of the North Sea where the water depth ranging from 20 to 35 meters. PHILOSOPHY: The design shall allow for re-use after field depletion Lifecycle cost shall always be considered Simple installation/de-installation methodology  An ergonomic acceptable lay out Free water knock out  Renewable energy Iv-Oil & Gas www.iv-groep.nl
PROJECT MANAGEMENT  ● ENGINEERING  ● CONTRACTING INTRODUCTION STUDY OBJECTIVES Define a concept, Define a generic topside, Estimate topside weight and space requirements, Recommend a transport, assembly and installation method, Cover implementation aspects of project execution, Estimate capital expenditure.  Iv-Oil & Gas www.iv-groep.nl
PROJECT MANAGEMENT  ● ENGINEERING  ● CONTRACTING INTRODUCTION STUDY PARAMETERS Site data (20 to 35m water depth) Base process data (2 producing wells, 1.8 mln m 3 /d) Materials of construction (Duplex stainless steel) Utilities (Emergency diesel, solar cells and wind turbines) Emergency overnight shelter (4 persons) Design and fatigue life (20 years, Fatigue: x5, x10) Other (wire line operations, no crane) Iv-Oil & Gas www.iv-groep.nl
PROJECT MANAGEMENT  ● ENGINEERING  ● CONTRACTING SUBSTRUCTURES Iv-Oil & Gas www.iv-groep.nl
PROJECT MANAGEMENT  ● ENGINEERING  ● CONTRACTING SUBSTRUCTURES INSTALLATION OPTIONS Crane barge installed with driven piles Installed by jack-up rig or construction barge Self installing SUBSTRUCTURES Conventional multi-legged jacket Minimal braced tower jacket Conductor supported modular structure Monotower Self installing platforms Iv-Oil & Gas www.iv-groep.nl
PROJECT MANAGEMENT  ● ENGINEERING  ● CONTRACTING SUBSTRUCTURES CRANE/BARGE INSTALLED - MULTILEGGED JACKET Advantages Proven concept Supports all marginal topsides Can support work-over units Disadvantages Requires heavy lift vessel Main pile jackets require field welds High installation costs Iv-Oil & Gas www.iv-groep.nl
PROJECT MANAGEMENT  ● ENGINEERING  ● CONTRACTING SUBSTRUCTURES CRANE/BARGE INSTALLED – MINIMAL BRACED Advantages Low weight Disadvantages Requires heavy lift vessel Limited future expansion Jack-up rig required for work-over Iv-Oil & Gas www.iv-groep.nl
PROJECT MANAGEMENT  ● ENGINEERING  ● CONTRACTING SUBSTRUCTURES RIG/BARGE INSTALLED – CONDUCTOR SUPPORTED Advantages Cost effective  Disadvantages Topsides limited to 200 tonnes Permitting Not to be pursued Iv-Oil & Gas www.iv-groep.nl
PROJECT MANAGEMENT  ● ENGINEERING  ● CONTRACTING SUBSTRUCTURES RIG/BARGE INSTALLED – MONOTOWER Advantages Low weight Protected conductors and risers  Disadvantages Cannot pre-drill wells Work-over requires drilling rig Limited topside weight Sensitive to dynamic motions     fatigue    additional bracings Iv-Oil & Gas www.iv-groep.nl
PROJECT MANAGEMENT  ● ENGINEERING  ● CONTRACTING SUBSTRUCTURES SELF INSTALLING – SIP I Advantages Transport floating on suction piles Disadvantages Separately installed topsides Iv-Oil & Gas www.iv-groep.nl
PROJECT MANAGEMENT  ● ENGINEERING  ● CONTRACTING SUBSTRUCTURES SELF INSTALLING – SIP II Advantages No lifting required at location Docking over pre-drilled wells Re-usable Maximized onshore commissioning Disadvantages Too large to be considered marginal Larger deck width Iv-Oil & Gas www.iv-groep.nl
PROJECT MANAGEMENT  ● ENGINEERING  ● CONTRACTING SUBSTRUCTURES SELF INSTALLING – SIP III Advantages No heavy lift vessel Docking over pre-drilled wells Re-usable Maximized onshore commissioning Disadvantages Topside weight limited Temporary frame required on barge Iv-Oil & Gas www.iv-groep.nl
PROJECT MANAGEMENT  ● ENGINEERING  ● CONTRACTING SUBSTRUCTURES SELF INSTALLING – SIP IV Advantages No heavy lift vessel Docking over pre-drilled wells Re-usable Maximized onshore commissioning Disadvantages Deck and substructure weight too  high for a marginal concept Iv-Oil & Gas www.iv-groep.nl
PROJECT MANAGEMENT  ● ENGINEERING  ● CONTRACTING SUBSTRUCTURES CONCEPT SELECTION Installable without a heavy lift vessel Ability to support a 3-well 400 tonnes topside Low weight Minimum decommissioning costs The SIP 3 concept satisfies the criteria of the study and therefore it is selected as the preferred substructure for this study . Iv-Oil & Gas www.iv-groep.nl
PROJECT MANAGEMENT  ● ENGINEERING  ● CONTRACTING SIP 3 Iv-Oil & Gas www.iv-groep.nl
PROJECT MANAGEMENT  ● ENGINEERING  ● CONTRACTING SIP 3 SIP 3 CONCEPT SPT patent Barge installed, fully pre-installed and commissioned Iv-Oil & Gas www.iv-groep.nl
PROJECT MANAGEMENT  ● ENGINEERING  ● CONTRACTING SIP 3 SIP 3 SUBSTRUCTURE 3.5 m OD mono column, 3 suction piles Horizontal mono column orientation for fabrication Upending of the mono column from horizontal to vertical Vertical (lifted) load out with the suction piles attached Installation of topside (substructure at quay / harbour floor) Vertical transportation of the total platform Suitable transportation barge Docking over existing pre-drilled wells Future abandonment and re-installation Iv-Oil & Gas www.iv-groep.nl
PROJECT MANAGEMENT  ● ENGINEERING  ● CONTRACTING TOPSIDES Iv-Oil & Gas www.iv-groep.nl
PROJECT MANAGEMENT  ● ENGINEERING  ● CONTRACTING TOPSIDES SIP 3 TOPSIDES Main deck Intermediate deck Top deck (helideck) PROCESS 1.8 mln Nm 3 /d capacity MOC: 900# Duplex Free water Knockout (3 phase separation) Oil skimmer tank Clean water (<30 ppmv oil) overboard 10” pipeline Iv-Oil & Gas www.iv-groep.nl
PROJECT MANAGEMENT  ● ENGINEERING  ● CONTRACTING TOPSIDES CONTROL, SAFETY AND SHUT DOWN Unmanned autonomous operating classification Control via fibre optics by means of a DCS extension of  the host platform Gas detection and intruder alarm Rig connected deluge system (dry) H60 wall (E/I facilities and refuge) Iv-Oil & Gas www.iv-groep.nl
PROJECT MANAGEMENT  ● ENGINEERING  ● CONTRACTING TOPSIDES ENERGY 2400 watt energy consumption (unmanned mode) Renewable energy sources (wind turbines and solar) WEIGHT Topsides  : 340 tonnes Substructure : 860 tonnes Total  : 1200 tonnes Iv-Oil & Gas www.iv-groep.nl
PROJECT MANAGEMENT  ● ENGINEERING  ● CONTRACTING FABRICATION, TRANSPORT AND  INSTALLATION Iv-Oil & Gas www.iv-groep.nl
PROJECT MANAGEMENT  ● ENGINEERING  ● CONTRACTING FABRICATION, TRANSPORT AND  INSTALLATION FABRICATION Fabrication at a facility which has unrestricted access to the North Sea. Delivery of mono column (rolled and pre-welded) Delivery of suction piles  Fabrication substructure Integration of suction piles with the substructure Installation of sacrificial anodes Installation of SW pump, J-tube and riser inside column Iv-Oil & Gas www.iv-groep.nl
PROJECT MANAGEMENT  ● ENGINEERING  ● CONTRACTING FABRICATION, TRANSPORT AND  INSTALLATION TRANSPORT AND INSTALLATION Marine spread :  Main tow tug 60-80 TBP Assisting tug 40 TBP Barge 300 – 400 ft Strand jacks (4 x 600 ton) Suction pumps (3 x) Hang-off frame (at stern of barge) Mooring winches (4 x allows for accurate manoeuvring) ROV spread (seabed survey and wellhead inspection) Survey & positioning spread (platform position monitoring) Iv-Oil & Gas www.iv-groep.nl
PROJECT MANAGEMENT  ● ENGINEERING  ● CONTRACTING FABRICATION, TRANSPORT AND  INSTALLATION INSTALLATION OPTIONS Topside pre-installed at top of column, transport with barge SIP3, offshore lowered with strand jacks (1x jacking), Topside pre-installed at lower section of column, transport with barge SIP3, substructure lowered offshore using strand jacks, deck lifted with strand jacks (2x jacking), Topside installed at top of column, transport on barge, offshore single lift HLV/SSCV (1x lifting), Topside on barge, substructure on barge, offshore installation deck with sheerleg/HLV/SSCV (2x lifting), Transport topside on barge, substructure in hooks sheerleg (1x lowering, 1x lifting). Iv-Oil & Gas www.iv-groep.nl
PROJECT MANAGEMENT  ● ENGINEERING  ● CONTRACTING FABRICATION, TRANSPORT AND  INSTALLATION INSTALLATION The installation of the platform consists of the following phases: Preparation phase Barge mooring Platform lowering Foundation installation Completion activities Iv-Oil & Gas www.iv-groep.nl
PROJECT MANAGEMENT  ● ENGINEERING  ● CONTRACTING FABRICATION, TRANSPORT AND  INSTALLATION INSTALLATION Sea fastening of substructure to the barge using  hydraulic pins for swift release of the substructure  from the barge after mooring, Tow to the field using tugs, Transport positive range of stability more than 50 degrees (criterion > 36 degrees), Lowering stability (hydrostatic and hydrodynamic) provided by ballast on the suction piles, Lowering and lifting systems using strand jacks, Suction pumps for the installation and future removal of  the suction pile foundation, No divers required for installation and removal of  installation equipment. Iv-Oil & Gas www.iv-groep.nl
PROJECT MANAGEMENT  ● ENGINEERING  ● CONTRACTING SCHEDULE Iv-Oil & Gas www.iv-groep.nl
PROJECT MANAGEMENT  ● ENGINEERING  ● CONTRACTING SCHEDULE DEFINITION OF PROJECT PHASES Conceptual design Detail design Procurement Construction Onshore test/commissioning Transportation and installation Iv-Oil & Gas www.iv-groep.nl
PROJECT MANAGEMENT  ● ENGINEERING  ● CONTRACTING SCHEDULE CONCEPT PLANNING Iv-Oil & Gas www.iv-groep.nl
PROJECT MANAGEMENT  ● ENGINEERING  ● CONTRACTING COST ESTIMATE Iv-Oil & Gas www.iv-groep.nl
PROJECT MANAGEMENT  ● ENGINEERING  ● CONTRACTING COST ESTIMATE OVERVIEW Iv-Oil & Gas www.iv-groep.nl --- --- --- --- Grand Total           --- ---     Overall contingency ~15% --- ---     Certification  --- ---     Insurance  --- ---     Fabrication and installation --- ---     Design & Procurement --- --- --- --- Equipment (incl commisioning) ---   --- --- Helideck ---   --- --- Topsides structual steel ---   --- --- Substructure (€·10 3 ) (€·10 3 ) (€·10 3 ) (€·10 3 )     costs costs Total Other Fabrication  FoB Description
PROJECT MANAGEMENT  ● ENGINEERING  ● CONTRACTING END OF PRESENTATION QUESTIONS? Iv-Oil & Gas www.iv-groep.nl

More Related Content

What's hot

1 ior-eor rd-plans
1 ior-eor  rd-plans1 ior-eor  rd-plans
1 ior-eor rd-plans
Guillermo Daniel Criniti
 
Enhached oil recovery EOR
Enhached oil recovery EOREnhached oil recovery EOR
Enhached oil recovery EOR
Hendri Anur
 
Basic whp presentation(1)
Basic whp presentation(1)Basic whp presentation(1)
Basic whp presentation(1)
nguyen_uptorcem
 
Engineering of Subsea Production Systems
Engineering of Subsea Production SystemsEngineering of Subsea Production Systems
Engineering of Subsea Production Systems
petroEDGE
 
Subsea completion and control system
Subsea completion and control systemSubsea completion and control system
Subsea completion and control system
Amit Nitharwal
 
Scsssv surface control subsurface safety valve
Scsssv surface control subsurface safety valveScsssv surface control subsurface safety valve
Scsssv surface control subsurface safety valve
Elsayed Amer
 
Offshore oil and gas overview
Offshore oil and gas overviewOffshore oil and gas overview
Offshore oil and gas overview
minh nguyễn
 
Field Development Plan
Field Development PlanField Development Plan
Field Development Plan
Mahmood Ajabbar
 
Basics_of_petroleum_Engineering_for_well.ppt
Basics_of_petroleum_Engineering_for_well.pptBasics_of_petroleum_Engineering_for_well.ppt
Basics_of_petroleum_Engineering_for_well.ppt
BadeesGhazal
 
Subsea Separation presentation
Subsea Separation presentationSubsea Separation presentation
Subsea Separation presentation
Sunday Kanshio, PhD
 
Well planning
Well planningWell planning
waterflooding (www.mpetro.ir)
waterflooding (www.mpetro.ir)waterflooding (www.mpetro.ir)
waterflooding (www.mpetro.ir)
mpetroleum
 
Sequence of well completion part 1
Sequence of well completion part 1Sequence of well completion part 1
Sequence of well completion part 1
Elsayed Amer
 
Floting Production Storage and Offloading
Floting Production Storage  and OffloadingFloting Production Storage  and Offloading
Floting Production Storage and Offloading
Indian Maritime University, Visakhapatnam
 
subsea
subseasubsea
subsea
densands
 
Oil And Gas Processing
Oil And Gas ProcessingOil And Gas Processing
Oil And Gas Processing
mubarak2009
 
PENNGLEN FIELD Development Plan (GULF of MEXICO)
PENNGLEN FIELD Development Plan (GULF of MEXICO)PENNGLEN FIELD Development Plan (GULF of MEXICO)
PENNGLEN FIELD Development Plan (GULF of MEXICO)
PaulOkafor6
 
Marginal oil fields
Marginal oil fieldsMarginal oil fields
Marginal oil fields
Kareem Mamdouh
 
Introduction to Offshore Oil and Gas Surface Facilities
Introduction to Offshore Oil and Gas Surface FacilitiesIntroduction to Offshore Oil and Gas Surface Facilities
Introduction to Offshore Oil and Gas Surface Facilities
Ir. Puput Risanto, IPM, PMP, PMI-RMP, ASEAN Eng
 
Side sliding door ssd
Side sliding door ssdSide sliding door ssd
Side sliding door ssd
Elsayed Amer
 

What's hot (20)

1 ior-eor rd-plans
1 ior-eor  rd-plans1 ior-eor  rd-plans
1 ior-eor rd-plans
 
Enhached oil recovery EOR
Enhached oil recovery EOREnhached oil recovery EOR
Enhached oil recovery EOR
 
Basic whp presentation(1)
Basic whp presentation(1)Basic whp presentation(1)
Basic whp presentation(1)
 
Engineering of Subsea Production Systems
Engineering of Subsea Production SystemsEngineering of Subsea Production Systems
Engineering of Subsea Production Systems
 
Subsea completion and control system
Subsea completion and control systemSubsea completion and control system
Subsea completion and control system
 
Scsssv surface control subsurface safety valve
Scsssv surface control subsurface safety valveScsssv surface control subsurface safety valve
Scsssv surface control subsurface safety valve
 
Offshore oil and gas overview
Offshore oil and gas overviewOffshore oil and gas overview
Offshore oil and gas overview
 
Field Development Plan
Field Development PlanField Development Plan
Field Development Plan
 
Basics_of_petroleum_Engineering_for_well.ppt
Basics_of_petroleum_Engineering_for_well.pptBasics_of_petroleum_Engineering_for_well.ppt
Basics_of_petroleum_Engineering_for_well.ppt
 
Subsea Separation presentation
Subsea Separation presentationSubsea Separation presentation
Subsea Separation presentation
 
Well planning
Well planningWell planning
Well planning
 
waterflooding (www.mpetro.ir)
waterflooding (www.mpetro.ir)waterflooding (www.mpetro.ir)
waterflooding (www.mpetro.ir)
 
Sequence of well completion part 1
Sequence of well completion part 1Sequence of well completion part 1
Sequence of well completion part 1
 
Floting Production Storage and Offloading
Floting Production Storage  and OffloadingFloting Production Storage  and Offloading
Floting Production Storage and Offloading
 
subsea
subseasubsea
subsea
 
Oil And Gas Processing
Oil And Gas ProcessingOil And Gas Processing
Oil And Gas Processing
 
PENNGLEN FIELD Development Plan (GULF of MEXICO)
PENNGLEN FIELD Development Plan (GULF of MEXICO)PENNGLEN FIELD Development Plan (GULF of MEXICO)
PENNGLEN FIELD Development Plan (GULF of MEXICO)
 
Marginal oil fields
Marginal oil fieldsMarginal oil fields
Marginal oil fields
 
Introduction to Offshore Oil and Gas Surface Facilities
Introduction to Offshore Oil and Gas Surface FacilitiesIntroduction to Offshore Oil and Gas Surface Facilities
Introduction to Offshore Oil and Gas Surface Facilities
 
Side sliding door ssd
Side sliding door ssdSide sliding door ssd
Side sliding door ssd
 

Viewers also liked

REAL OPTIONS ANALYSIS OF MARGINAL OILFIELD DEVELOPMENT PROJECTS: THE CASE OF ...
REAL OPTIONS ANALYSIS OF MARGINAL OILFIELD DEVELOPMENT PROJECTS: THE CASE OF ...REAL OPTIONS ANALYSIS OF MARGINAL OILFIELD DEVELOPMENT PROJECTS: THE CASE OF ...
REAL OPTIONS ANALYSIS OF MARGINAL OILFIELD DEVELOPMENT PROJECTS: THE CASE OF ...
Theo Acheampong
 
PE929 Marginal Offshore Field Development
PE929 Marginal Offshore Field DevelopmentPE929 Marginal Offshore Field Development
PE929 Marginal Offshore Field Development
petroEDGE
 
Offshore Structures Presentation
Offshore Structures PresentationOffshore Structures Presentation
Offshore Structures Presentation
surya3303
 
Drillships
DrillshipsDrillships
Offshore Platforms
Offshore Platforms Offshore Platforms
Oil Industry Powerpoint Template
Oil Industry Powerpoint TemplateOil Industry Powerpoint Template
Oil Industry Powerpoint Template
PowerPoint Team
 
Offshore platform-design
Offshore platform-designOffshore platform-design
Offshore platform-design
Rahul Ranakoti
 
Tud dimi general presentation-2010-2011_v2.2
Tud dimi general presentation-2010-2011_v2.2Tud dimi general presentation-2010-2011_v2.2
Tud dimi general presentation-2010-2011_v2.2
Delft Infrastructures & Mobility Initiative
 
07 closure of the opening ceremony by tiedo vellinga
07 closure of the opening ceremony by tiedo vellinga07 closure of the opening ceremony by tiedo vellinga
07 closure of the opening ceremony by tiedo vellinga
Delft Infrastructures & Mobility Initiative
 
02 tsl from tender until rfc by pablo arecco
02 tsl from tender until rfc by pablo arecco02 tsl from tender until rfc by pablo arecco
02 tsl from tender until rfc by pablo arecco
Delft Infrastructures & Mobility Initiative
 
Project assurance - make sure your projects delivers as expected
Project assurance - make sure your projects delivers as expectedProject assurance - make sure your projects delivers as expected
Project assurance - make sure your projects delivers as expected
Terje Sæbø
 
Missile tom
Missile tomMissile tom
Missile tom
hindujudaic
 
Red Sea - Dead Sea Water Conveyance - Feasibility Study - report summary
Red Sea - Dead Sea Water Conveyance - Feasibility Study - report summaryRed Sea - Dead Sea Water Conveyance - Feasibility Study - report summary
Red Sea - Dead Sea Water Conveyance - Feasibility Study - report summary
asafeiran
 
Recession poll 2011 const oilmininggas_final
Recession poll 2011 const oilmininggas_finalRecession poll 2011 const oilmininggas_final
Recession poll 2011 const oilmininggas_final
shrm
 
Oil Gas Companies in Indonesia: Ready for The New Normal?
Oil Gas Companies in Indonesia: Ready for The New Normal?Oil Gas Companies in Indonesia: Ready for The New Normal?
Oil Gas Companies in Indonesia: Ready for The New Normal?
Gede Manggala
 
Design & operation of topsides gas field
Design & operation of topsides gas fieldDesign & operation of topsides gas field
Design & operation of topsides gas field
ashutoshgugnani
 
Post Recession Offshore - Oil & Gas Industry
Post Recession Offshore - Oil & Gas IndustryPost Recession Offshore - Oil & Gas Industry
Post Recession Offshore - Oil & Gas Industry
Aftab Hasan
 
marine coastal structures
marine coastal structuresmarine coastal structures
marine coastal structures
Shirsak Mondal
 
Horizon 2020
Horizon 2020Horizon 2020
Horizon 2020
Pomcert
 
Trawler report
Trawler reportTrawler report
Trawler report
Sainath Nashikkar
 

Viewers also liked (20)

REAL OPTIONS ANALYSIS OF MARGINAL OILFIELD DEVELOPMENT PROJECTS: THE CASE OF ...
REAL OPTIONS ANALYSIS OF MARGINAL OILFIELD DEVELOPMENT PROJECTS: THE CASE OF ...REAL OPTIONS ANALYSIS OF MARGINAL OILFIELD DEVELOPMENT PROJECTS: THE CASE OF ...
REAL OPTIONS ANALYSIS OF MARGINAL OILFIELD DEVELOPMENT PROJECTS: THE CASE OF ...
 
PE929 Marginal Offshore Field Development
PE929 Marginal Offshore Field DevelopmentPE929 Marginal Offshore Field Development
PE929 Marginal Offshore Field Development
 
Offshore Structures Presentation
Offshore Structures PresentationOffshore Structures Presentation
Offshore Structures Presentation
 
Drillships
DrillshipsDrillships
Drillships
 
Offshore Platforms
Offshore Platforms Offshore Platforms
Offshore Platforms
 
Oil Industry Powerpoint Template
Oil Industry Powerpoint TemplateOil Industry Powerpoint Template
Oil Industry Powerpoint Template
 
Offshore platform-design
Offshore platform-designOffshore platform-design
Offshore platform-design
 
Tud dimi general presentation-2010-2011_v2.2
Tud dimi general presentation-2010-2011_v2.2Tud dimi general presentation-2010-2011_v2.2
Tud dimi general presentation-2010-2011_v2.2
 
07 closure of the opening ceremony by tiedo vellinga
07 closure of the opening ceremony by tiedo vellinga07 closure of the opening ceremony by tiedo vellinga
07 closure of the opening ceremony by tiedo vellinga
 
02 tsl from tender until rfc by pablo arecco
02 tsl from tender until rfc by pablo arecco02 tsl from tender until rfc by pablo arecco
02 tsl from tender until rfc by pablo arecco
 
Project assurance - make sure your projects delivers as expected
Project assurance - make sure your projects delivers as expectedProject assurance - make sure your projects delivers as expected
Project assurance - make sure your projects delivers as expected
 
Missile tom
Missile tomMissile tom
Missile tom
 
Red Sea - Dead Sea Water Conveyance - Feasibility Study - report summary
Red Sea - Dead Sea Water Conveyance - Feasibility Study - report summaryRed Sea - Dead Sea Water Conveyance - Feasibility Study - report summary
Red Sea - Dead Sea Water Conveyance - Feasibility Study - report summary
 
Recession poll 2011 const oilmininggas_final
Recession poll 2011 const oilmininggas_finalRecession poll 2011 const oilmininggas_final
Recession poll 2011 const oilmininggas_final
 
Oil Gas Companies in Indonesia: Ready for The New Normal?
Oil Gas Companies in Indonesia: Ready for The New Normal?Oil Gas Companies in Indonesia: Ready for The New Normal?
Oil Gas Companies in Indonesia: Ready for The New Normal?
 
Design & operation of topsides gas field
Design & operation of topsides gas fieldDesign & operation of topsides gas field
Design & operation of topsides gas field
 
Post Recession Offshore - Oil & Gas Industry
Post Recession Offshore - Oil & Gas IndustryPost Recession Offshore - Oil & Gas Industry
Post Recession Offshore - Oil & Gas Industry
 
marine coastal structures
marine coastal structuresmarine coastal structures
marine coastal structures
 
Horizon 2020
Horizon 2020Horizon 2020
Horizon 2020
 
Trawler report
Trawler reportTrawler report
Trawler report
 

Similar to Marginal offshore production platform feasibility

Marginal satellite study Noordzee
Marginal satellite study NoordzeeMarginal satellite study Noordzee
Marginal satellite study Noordzee
Sander_van_oirschot
 
MOQ Platform installation_Lesson learnt_Rev B
MOQ Platform installation_Lesson learnt_Rev BMOQ Platform installation_Lesson learnt_Rev B
MOQ Platform installation_Lesson learnt_Rev B
Vishak Gopi
 
000-GENERAL presentation_rev06
000-GENERAL presentation_rev06000-GENERAL presentation_rev06
000-GENERAL presentation_rev06
Stefan Erents
 
Richard Turnbull CV Supplement 2012
Richard Turnbull CV Supplement 2012Richard Turnbull CV Supplement 2012
Richard Turnbull CV Supplement 2012
Richard Turnbull
 
Master präsentation pal sys-offshore
Master präsentation pal sys-offshoreMaster präsentation pal sys-offshore
Master präsentation pal sys-offshore
Benji George
 
Sal offshore brochure_2016-05-03_web
Sal offshore brochure_2016-05-03_webSal offshore brochure_2016-05-03_web
Sal offshore brochure_2016-05-03_web
Nora Kohlhase
 
Sal offshore brochure_2016-05-03_web
Sal offshore brochure_2016-05-03_webSal offshore brochure_2016-05-03_web
Sal offshore brochure_2016-05-03_web
Paul Heinrich
 
Offshore platforms
Offshore platformsOffshore platforms
Offshore platforms
RaviNobleseas
 
Euro-Rigging presentation 2013
Euro-Rigging presentation 2013Euro-Rigging presentation 2013
Euro-Rigging presentation 2013
wesseln
 
Metode Konstruksi Offshore Platform_2016_2_18.ppt
Metode Konstruksi Offshore Platform_2016_2_18.pptMetode Konstruksi Offshore Platform_2016_2_18.ppt
Metode Konstruksi Offshore Platform_2016_2_18.ppt
MFaridGeonova
 
Project mechanical engineer c.v
Project mechanical engineer c.vProject mechanical engineer c.v
Project mechanical engineer c.v
ali ibrahim
 
Project Mechanical Engineer C.V
Project Mechanical Engineer C.VProject Mechanical Engineer C.V
Project Mechanical Engineer C.V
ali ibrahim
 
Vedam Designs: Solutions for Shallow Water maintenance Dredging
Vedam Designs: Solutions for Shallow Water maintenance DredgingVedam Designs: Solutions for Shallow Water maintenance Dredging
Vedam Designs: Solutions for Shallow Water maintenance Dredging
Vedam design & Techincal Consultancy Pvt Ltd.
 
Petroleum drilling fundamentals
Petroleum drilling fundamentalsPetroleum drilling fundamentals
Petroleum drilling fundamentals
Sigve Hamilton Aspelund
 
Portfolio - Theodoros Dragonas - Mechanical Design Engineer
Portfolio - Theodoros Dragonas - Mechanical Design EngineerPortfolio - Theodoros Dragonas - Mechanical Design Engineer
Portfolio - Theodoros Dragonas - Mechanical Design Engineer
Theodoros Dragonas
 
Innovative, faster and safer access solutions for jack-up-rig leg works - OJ...
Innovative, faster and safer access solutions for jack-up-rig leg works - OJ...Innovative, faster and safer access solutions for jack-up-rig leg works - OJ...
Innovative, faster and safer access solutions for jack-up-rig leg works - OJ...
Benji George
 
OFFSHORE CV DYLAN OLIVIER UPDATE Oct 2014
OFFSHORE CV DYLAN OLIVIER UPDATE Oct 2014OFFSHORE CV DYLAN OLIVIER UPDATE Oct 2014
OFFSHORE CV DYLAN OLIVIER UPDATE Oct 2014
Dylan Olivier
 
RINA - AOG 2017 - Development of Self Installing Deepwater Spar - ARUP - Ashi...
RINA - AOG 2017 - Development of Self Installing Deepwater Spar - ARUP - Ashi...RINA - AOG 2017 - Development of Self Installing Deepwater Spar - ARUP - Ashi...
RINA - AOG 2017 - Development of Self Installing Deepwater Spar - ARUP - Ashi...
Nick Bentley
 
SDI Kuwait Causeway prj.(kusc)
SDI Kuwait Causeway prj.(kusc)SDI Kuwait Causeway prj.(kusc)
SDI Kuwait Causeway prj.(kusc)
Aquilino Raimundo
 
SDI Kuwait Causeway prj.(kusc)
SDI Kuwait Causeway prj.(kusc)SDI Kuwait Causeway prj.(kusc)
SDI Kuwait Causeway prj.(kusc)
Strukturas
 

Similar to Marginal offshore production platform feasibility (20)

Marginal satellite study Noordzee
Marginal satellite study NoordzeeMarginal satellite study Noordzee
Marginal satellite study Noordzee
 
MOQ Platform installation_Lesson learnt_Rev B
MOQ Platform installation_Lesson learnt_Rev BMOQ Platform installation_Lesson learnt_Rev B
MOQ Platform installation_Lesson learnt_Rev B
 
000-GENERAL presentation_rev06
000-GENERAL presentation_rev06000-GENERAL presentation_rev06
000-GENERAL presentation_rev06
 
Richard Turnbull CV Supplement 2012
Richard Turnbull CV Supplement 2012Richard Turnbull CV Supplement 2012
Richard Turnbull CV Supplement 2012
 
Master präsentation pal sys-offshore
Master präsentation pal sys-offshoreMaster präsentation pal sys-offshore
Master präsentation pal sys-offshore
 
Sal offshore brochure_2016-05-03_web
Sal offshore brochure_2016-05-03_webSal offshore brochure_2016-05-03_web
Sal offshore brochure_2016-05-03_web
 
Sal offshore brochure_2016-05-03_web
Sal offshore brochure_2016-05-03_webSal offshore brochure_2016-05-03_web
Sal offshore brochure_2016-05-03_web
 
Offshore platforms
Offshore platformsOffshore platforms
Offshore platforms
 
Euro-Rigging presentation 2013
Euro-Rigging presentation 2013Euro-Rigging presentation 2013
Euro-Rigging presentation 2013
 
Metode Konstruksi Offshore Platform_2016_2_18.ppt
Metode Konstruksi Offshore Platform_2016_2_18.pptMetode Konstruksi Offshore Platform_2016_2_18.ppt
Metode Konstruksi Offshore Platform_2016_2_18.ppt
 
Project mechanical engineer c.v
Project mechanical engineer c.vProject mechanical engineer c.v
Project mechanical engineer c.v
 
Project Mechanical Engineer C.V
Project Mechanical Engineer C.VProject Mechanical Engineer C.V
Project Mechanical Engineer C.V
 
Vedam Designs: Solutions for Shallow Water maintenance Dredging
Vedam Designs: Solutions for Shallow Water maintenance DredgingVedam Designs: Solutions for Shallow Water maintenance Dredging
Vedam Designs: Solutions for Shallow Water maintenance Dredging
 
Petroleum drilling fundamentals
Petroleum drilling fundamentalsPetroleum drilling fundamentals
Petroleum drilling fundamentals
 
Portfolio - Theodoros Dragonas - Mechanical Design Engineer
Portfolio - Theodoros Dragonas - Mechanical Design EngineerPortfolio - Theodoros Dragonas - Mechanical Design Engineer
Portfolio - Theodoros Dragonas - Mechanical Design Engineer
 
Innovative, faster and safer access solutions for jack-up-rig leg works - OJ...
Innovative, faster and safer access solutions for jack-up-rig leg works - OJ...Innovative, faster and safer access solutions for jack-up-rig leg works - OJ...
Innovative, faster and safer access solutions for jack-up-rig leg works - OJ...
 
OFFSHORE CV DYLAN OLIVIER UPDATE Oct 2014
OFFSHORE CV DYLAN OLIVIER UPDATE Oct 2014OFFSHORE CV DYLAN OLIVIER UPDATE Oct 2014
OFFSHORE CV DYLAN OLIVIER UPDATE Oct 2014
 
RINA - AOG 2017 - Development of Self Installing Deepwater Spar - ARUP - Ashi...
RINA - AOG 2017 - Development of Self Installing Deepwater Spar - ARUP - Ashi...RINA - AOG 2017 - Development of Self Installing Deepwater Spar - ARUP - Ashi...
RINA - AOG 2017 - Development of Self Installing Deepwater Spar - ARUP - Ashi...
 
SDI Kuwait Causeway prj.(kusc)
SDI Kuwait Causeway prj.(kusc)SDI Kuwait Causeway prj.(kusc)
SDI Kuwait Causeway prj.(kusc)
 
SDI Kuwait Causeway prj.(kusc)
SDI Kuwait Causeway prj.(kusc)SDI Kuwait Causeway prj.(kusc)
SDI Kuwait Causeway prj.(kusc)
 

Recently uploaded

IPLOOK Remote-Sensing Satellite Solution
IPLOOK Remote-Sensing Satellite SolutionIPLOOK Remote-Sensing Satellite Solution
IPLOOK Remote-Sensing Satellite Solution
IPLOOK Networks
 
WhatsApp Spy Online Trackers and Monitoring Apps
WhatsApp Spy Online Trackers and Monitoring AppsWhatsApp Spy Online Trackers and Monitoring Apps
WhatsApp Spy Online Trackers and Monitoring Apps
HackersList
 
Recent Advancements in the NIST-JARVIS Infrastructure
Recent Advancements in the NIST-JARVIS InfrastructureRecent Advancements in the NIST-JARVIS Infrastructure
Recent Advancements in the NIST-JARVIS Infrastructure
KAMAL CHOUDHARY
 
How Social Media Hackers Help You to See Your Wife's Message.pdf
How Social Media Hackers Help You to See Your Wife's Message.pdfHow Social Media Hackers Help You to See Your Wife's Message.pdf
How Social Media Hackers Help You to See Your Wife's Message.pdf
HackersList
 
[Talk] Moving Beyond Spaghetti Infrastructure [AOTB] 2024-07-04.pdf
[Talk] Moving Beyond Spaghetti Infrastructure [AOTB] 2024-07-04.pdf[Talk] Moving Beyond Spaghetti Infrastructure [AOTB] 2024-07-04.pdf
[Talk] Moving Beyond Spaghetti Infrastructure [AOTB] 2024-07-04.pdf
Kief Morris
 
High Profile Girls Call ServiCe Hyderabad 0000000000 Tanisha Best High Class ...
High Profile Girls Call ServiCe Hyderabad 0000000000 Tanisha Best High Class ...High Profile Girls Call ServiCe Hyderabad 0000000000 Tanisha Best High Class ...
High Profile Girls Call ServiCe Hyderabad 0000000000 Tanisha Best High Class ...
aslasdfmkhan4750
 
TrustArc Webinar - 2024 Data Privacy Trends: A Mid-Year Check-In
TrustArc Webinar - 2024 Data Privacy Trends: A Mid-Year Check-InTrustArc Webinar - 2024 Data Privacy Trends: A Mid-Year Check-In
TrustArc Webinar - 2024 Data Privacy Trends: A Mid-Year Check-In
TrustArc
 
“Deploying Large Language Models on a Raspberry Pi,” a Presentation from Usef...
“Deploying Large Language Models on a Raspberry Pi,” a Presentation from Usef...“Deploying Large Language Models on a Raspberry Pi,” a Presentation from Usef...
“Deploying Large Language Models on a Raspberry Pi,” a Presentation from Usef...
Edge AI and Vision Alliance
 
High Profile Girls call Service Pune 000XX00000 Provide Best And Top Girl Ser...
High Profile Girls call Service Pune 000XX00000 Provide Best And Top Girl Ser...High Profile Girls call Service Pune 000XX00000 Provide Best And Top Girl Ser...
High Profile Girls call Service Pune 000XX00000 Provide Best And Top Girl Ser...
bhumivarma35300
 
Opencast Summit 2024 — Opencast @ University of Münster
Opencast Summit 2024 — Opencast @ University of MünsterOpencast Summit 2024 — Opencast @ University of Münster
Opencast Summit 2024 — Opencast @ University of Münster
Matthias Neugebauer
 
Data Integration Basics: Merging & Joining Data
Data Integration Basics: Merging & Joining DataData Integration Basics: Merging & Joining Data
Data Integration Basics: Merging & Joining Data
Safe Software
 
How to Build a Profitable IoT Product.pptx
How to Build a Profitable IoT Product.pptxHow to Build a Profitable IoT Product.pptx
How to Build a Profitable IoT Product.pptx
Adam Dunkels
 
(CISOPlatform Summit & SACON 2024) Keynote _ Power Digital Identities With AI...
(CISOPlatform Summit & SACON 2024) Keynote _ Power Digital Identities With AI...(CISOPlatform Summit & SACON 2024) Keynote _ Power Digital Identities With AI...
(CISOPlatform Summit & SACON 2024) Keynote _ Power Digital Identities With AI...
Priyanka Aash
 
Uncharted Together- Navigating AI's New Frontiers in Libraries
Uncharted Together- Navigating AI's New Frontiers in LibrariesUncharted Together- Navigating AI's New Frontiers in Libraries
Uncharted Together- Navigating AI's New Frontiers in Libraries
Brian Pichman
 
The Role of IoT in Australian Mobile App Development - PDF Guide
The Role of IoT in Australian Mobile App Development - PDF GuideThe Role of IoT in Australian Mobile App Development - PDF Guide
The Role of IoT in Australian Mobile App Development - PDF Guide
Shiv Technolabs
 
Use Cases & Benefits of RPA in Manufacturing in 2024.pptx
Use Cases & Benefits of RPA in Manufacturing in 2024.pptxUse Cases & Benefits of RPA in Manufacturing in 2024.pptx
Use Cases & Benefits of RPA in Manufacturing in 2024.pptx
SynapseIndia
 
Three New Criminal Laws in India 1 July 2024
Three New Criminal Laws in India 1 July 2024Three New Criminal Laws in India 1 July 2024
Three New Criminal Laws in India 1 July 2024
aakash malhotra
 
Salesforce AI & Einstein Copilot Workshop
Salesforce AI & Einstein Copilot WorkshopSalesforce AI & Einstein Copilot Workshop
Salesforce AI & Einstein Copilot Workshop
CEPTES Software Inc
 
BT & Neo4j: Knowledge Graphs for Critical Enterprise Systems.pptx.pdf
BT & Neo4j: Knowledge Graphs for Critical Enterprise Systems.pptx.pdfBT & Neo4j: Knowledge Graphs for Critical Enterprise Systems.pptx.pdf
BT & Neo4j: Knowledge Graphs for Critical Enterprise Systems.pptx.pdf
Neo4j
 
Active Inference is a veryyyyyyyyyyyyyyyyyyyyyyyy
Active Inference is a veryyyyyyyyyyyyyyyyyyyyyyyyActive Inference is a veryyyyyyyyyyyyyyyyyyyyyyyy
Active Inference is a veryyyyyyyyyyyyyyyyyyyyyyyy
RaminGhanbari2
 

Recently uploaded (20)

IPLOOK Remote-Sensing Satellite Solution
IPLOOK Remote-Sensing Satellite SolutionIPLOOK Remote-Sensing Satellite Solution
IPLOOK Remote-Sensing Satellite Solution
 
WhatsApp Spy Online Trackers and Monitoring Apps
WhatsApp Spy Online Trackers and Monitoring AppsWhatsApp Spy Online Trackers and Monitoring Apps
WhatsApp Spy Online Trackers and Monitoring Apps
 
Recent Advancements in the NIST-JARVIS Infrastructure
Recent Advancements in the NIST-JARVIS InfrastructureRecent Advancements in the NIST-JARVIS Infrastructure
Recent Advancements in the NIST-JARVIS Infrastructure
 
How Social Media Hackers Help You to See Your Wife's Message.pdf
How Social Media Hackers Help You to See Your Wife's Message.pdfHow Social Media Hackers Help You to See Your Wife's Message.pdf
How Social Media Hackers Help You to See Your Wife's Message.pdf
 
[Talk] Moving Beyond Spaghetti Infrastructure [AOTB] 2024-07-04.pdf
[Talk] Moving Beyond Spaghetti Infrastructure [AOTB] 2024-07-04.pdf[Talk] Moving Beyond Spaghetti Infrastructure [AOTB] 2024-07-04.pdf
[Talk] Moving Beyond Spaghetti Infrastructure [AOTB] 2024-07-04.pdf
 
High Profile Girls Call ServiCe Hyderabad 0000000000 Tanisha Best High Class ...
High Profile Girls Call ServiCe Hyderabad 0000000000 Tanisha Best High Class ...High Profile Girls Call ServiCe Hyderabad 0000000000 Tanisha Best High Class ...
High Profile Girls Call ServiCe Hyderabad 0000000000 Tanisha Best High Class ...
 
TrustArc Webinar - 2024 Data Privacy Trends: A Mid-Year Check-In
TrustArc Webinar - 2024 Data Privacy Trends: A Mid-Year Check-InTrustArc Webinar - 2024 Data Privacy Trends: A Mid-Year Check-In
TrustArc Webinar - 2024 Data Privacy Trends: A Mid-Year Check-In
 
“Deploying Large Language Models on a Raspberry Pi,” a Presentation from Usef...
“Deploying Large Language Models on a Raspberry Pi,” a Presentation from Usef...“Deploying Large Language Models on a Raspberry Pi,” a Presentation from Usef...
“Deploying Large Language Models on a Raspberry Pi,” a Presentation from Usef...
 
High Profile Girls call Service Pune 000XX00000 Provide Best And Top Girl Ser...
High Profile Girls call Service Pune 000XX00000 Provide Best And Top Girl Ser...High Profile Girls call Service Pune 000XX00000 Provide Best And Top Girl Ser...
High Profile Girls call Service Pune 000XX00000 Provide Best And Top Girl Ser...
 
Opencast Summit 2024 — Opencast @ University of Münster
Opencast Summit 2024 — Opencast @ University of MünsterOpencast Summit 2024 — Opencast @ University of Münster
Opencast Summit 2024 — Opencast @ University of Münster
 
Data Integration Basics: Merging & Joining Data
Data Integration Basics: Merging & Joining DataData Integration Basics: Merging & Joining Data
Data Integration Basics: Merging & Joining Data
 
How to Build a Profitable IoT Product.pptx
How to Build a Profitable IoT Product.pptxHow to Build a Profitable IoT Product.pptx
How to Build a Profitable IoT Product.pptx
 
(CISOPlatform Summit & SACON 2024) Keynote _ Power Digital Identities With AI...
(CISOPlatform Summit & SACON 2024) Keynote _ Power Digital Identities With AI...(CISOPlatform Summit & SACON 2024) Keynote _ Power Digital Identities With AI...
(CISOPlatform Summit & SACON 2024) Keynote _ Power Digital Identities With AI...
 
Uncharted Together- Navigating AI's New Frontiers in Libraries
Uncharted Together- Navigating AI's New Frontiers in LibrariesUncharted Together- Navigating AI's New Frontiers in Libraries
Uncharted Together- Navigating AI's New Frontiers in Libraries
 
The Role of IoT in Australian Mobile App Development - PDF Guide
The Role of IoT in Australian Mobile App Development - PDF GuideThe Role of IoT in Australian Mobile App Development - PDF Guide
The Role of IoT in Australian Mobile App Development - PDF Guide
 
Use Cases & Benefits of RPA in Manufacturing in 2024.pptx
Use Cases & Benefits of RPA in Manufacturing in 2024.pptxUse Cases & Benefits of RPA in Manufacturing in 2024.pptx
Use Cases & Benefits of RPA in Manufacturing in 2024.pptx
 
Three New Criminal Laws in India 1 July 2024
Three New Criminal Laws in India 1 July 2024Three New Criminal Laws in India 1 July 2024
Three New Criminal Laws in India 1 July 2024
 
Salesforce AI & Einstein Copilot Workshop
Salesforce AI & Einstein Copilot WorkshopSalesforce AI & Einstein Copilot Workshop
Salesforce AI & Einstein Copilot Workshop
 
BT & Neo4j: Knowledge Graphs for Critical Enterprise Systems.pptx.pdf
BT & Neo4j: Knowledge Graphs for Critical Enterprise Systems.pptx.pdfBT & Neo4j: Knowledge Graphs for Critical Enterprise Systems.pptx.pdf
BT & Neo4j: Knowledge Graphs for Critical Enterprise Systems.pptx.pdf
 
Active Inference is a veryyyyyyyyyyyyyyyyyyyyyyyy
Active Inference is a veryyyyyyyyyyyyyyyyyyyyyyyyActive Inference is a veryyyyyyyyyyyyyyyyyyyyyyyy
Active Inference is a veryyyyyyyyyyyyyyyyyyyyyyyy
 

Marginal offshore production platform feasibility

  • 1. PROJECT MANAGEMENT ● ENGINEERING ● CONTRACTING Iv-Oil & Gas www.iv-groep.nl DEVELOPMENT OF A MARGINAL SATTELITE FIELD
  • 2. PROJECT MANAGEMENT ● ENGINEERING ● CONTRACTING INTRODUCTION Iv-Oil & Gas www.iv-groep.nl
  • 3. PROJECT MANAGEMENT ● ENGINEERING ● CONTRACTING INTRODUCTION Wintershall Noordzee BV is investigating the feasibility to utilize a low cost option to develop satellite fields located in the Dutch Sector of the North Sea where the water depth ranging from 20 to 35 meters. PHILOSOPHY: The design shall allow for re-use after field depletion Lifecycle cost shall always be considered Simple installation/de-installation methodology An ergonomic acceptable lay out Free water knock out Renewable energy Iv-Oil & Gas www.iv-groep.nl
  • 4. PROJECT MANAGEMENT ● ENGINEERING ● CONTRACTING INTRODUCTION STUDY OBJECTIVES Define a concept, Define a generic topside, Estimate topside weight and space requirements, Recommend a transport, assembly and installation method, Cover implementation aspects of project execution, Estimate capital expenditure. Iv-Oil & Gas www.iv-groep.nl
  • 5. PROJECT MANAGEMENT ● ENGINEERING ● CONTRACTING INTRODUCTION STUDY PARAMETERS Site data (20 to 35m water depth) Base process data (2 producing wells, 1.8 mln m 3 /d) Materials of construction (Duplex stainless steel) Utilities (Emergency diesel, solar cells and wind turbines) Emergency overnight shelter (4 persons) Design and fatigue life (20 years, Fatigue: x5, x10) Other (wire line operations, no crane) Iv-Oil & Gas www.iv-groep.nl
  • 6. PROJECT MANAGEMENT ● ENGINEERING ● CONTRACTING SUBSTRUCTURES Iv-Oil & Gas www.iv-groep.nl
  • 7. PROJECT MANAGEMENT ● ENGINEERING ● CONTRACTING SUBSTRUCTURES INSTALLATION OPTIONS Crane barge installed with driven piles Installed by jack-up rig or construction barge Self installing SUBSTRUCTURES Conventional multi-legged jacket Minimal braced tower jacket Conductor supported modular structure Monotower Self installing platforms Iv-Oil & Gas www.iv-groep.nl
  • 8. PROJECT MANAGEMENT ● ENGINEERING ● CONTRACTING SUBSTRUCTURES CRANE/BARGE INSTALLED - MULTILEGGED JACKET Advantages Proven concept Supports all marginal topsides Can support work-over units Disadvantages Requires heavy lift vessel Main pile jackets require field welds High installation costs Iv-Oil & Gas www.iv-groep.nl
  • 9. PROJECT MANAGEMENT ● ENGINEERING ● CONTRACTING SUBSTRUCTURES CRANE/BARGE INSTALLED – MINIMAL BRACED Advantages Low weight Disadvantages Requires heavy lift vessel Limited future expansion Jack-up rig required for work-over Iv-Oil & Gas www.iv-groep.nl
  • 10. PROJECT MANAGEMENT ● ENGINEERING ● CONTRACTING SUBSTRUCTURES RIG/BARGE INSTALLED – CONDUCTOR SUPPORTED Advantages Cost effective Disadvantages Topsides limited to 200 tonnes Permitting Not to be pursued Iv-Oil & Gas www.iv-groep.nl
  • 11. PROJECT MANAGEMENT ● ENGINEERING ● CONTRACTING SUBSTRUCTURES RIG/BARGE INSTALLED – MONOTOWER Advantages Low weight Protected conductors and risers Disadvantages Cannot pre-drill wells Work-over requires drilling rig Limited topside weight Sensitive to dynamic motions  fatigue  additional bracings Iv-Oil & Gas www.iv-groep.nl
  • 12. PROJECT MANAGEMENT ● ENGINEERING ● CONTRACTING SUBSTRUCTURES SELF INSTALLING – SIP I Advantages Transport floating on suction piles Disadvantages Separately installed topsides Iv-Oil & Gas www.iv-groep.nl
  • 13. PROJECT MANAGEMENT ● ENGINEERING ● CONTRACTING SUBSTRUCTURES SELF INSTALLING – SIP II Advantages No lifting required at location Docking over pre-drilled wells Re-usable Maximized onshore commissioning Disadvantages Too large to be considered marginal Larger deck width Iv-Oil & Gas www.iv-groep.nl
  • 14. PROJECT MANAGEMENT ● ENGINEERING ● CONTRACTING SUBSTRUCTURES SELF INSTALLING – SIP III Advantages No heavy lift vessel Docking over pre-drilled wells Re-usable Maximized onshore commissioning Disadvantages Topside weight limited Temporary frame required on barge Iv-Oil & Gas www.iv-groep.nl
  • 15. PROJECT MANAGEMENT ● ENGINEERING ● CONTRACTING SUBSTRUCTURES SELF INSTALLING – SIP IV Advantages No heavy lift vessel Docking over pre-drilled wells Re-usable Maximized onshore commissioning Disadvantages Deck and substructure weight too high for a marginal concept Iv-Oil & Gas www.iv-groep.nl
  • 16. PROJECT MANAGEMENT ● ENGINEERING ● CONTRACTING SUBSTRUCTURES CONCEPT SELECTION Installable without a heavy lift vessel Ability to support a 3-well 400 tonnes topside Low weight Minimum decommissioning costs The SIP 3 concept satisfies the criteria of the study and therefore it is selected as the preferred substructure for this study . Iv-Oil & Gas www.iv-groep.nl
  • 17. PROJECT MANAGEMENT ● ENGINEERING ● CONTRACTING SIP 3 Iv-Oil & Gas www.iv-groep.nl
  • 18. PROJECT MANAGEMENT ● ENGINEERING ● CONTRACTING SIP 3 SIP 3 CONCEPT SPT patent Barge installed, fully pre-installed and commissioned Iv-Oil & Gas www.iv-groep.nl
  • 19. PROJECT MANAGEMENT ● ENGINEERING ● CONTRACTING SIP 3 SIP 3 SUBSTRUCTURE 3.5 m OD mono column, 3 suction piles Horizontal mono column orientation for fabrication Upending of the mono column from horizontal to vertical Vertical (lifted) load out with the suction piles attached Installation of topside (substructure at quay / harbour floor) Vertical transportation of the total platform Suitable transportation barge Docking over existing pre-drilled wells Future abandonment and re-installation Iv-Oil & Gas www.iv-groep.nl
  • 20. PROJECT MANAGEMENT ● ENGINEERING ● CONTRACTING TOPSIDES Iv-Oil & Gas www.iv-groep.nl
  • 21. PROJECT MANAGEMENT ● ENGINEERING ● CONTRACTING TOPSIDES SIP 3 TOPSIDES Main deck Intermediate deck Top deck (helideck) PROCESS 1.8 mln Nm 3 /d capacity MOC: 900# Duplex Free water Knockout (3 phase separation) Oil skimmer tank Clean water (<30 ppmv oil) overboard 10” pipeline Iv-Oil & Gas www.iv-groep.nl
  • 22. PROJECT MANAGEMENT ● ENGINEERING ● CONTRACTING TOPSIDES CONTROL, SAFETY AND SHUT DOWN Unmanned autonomous operating classification Control via fibre optics by means of a DCS extension of the host platform Gas detection and intruder alarm Rig connected deluge system (dry) H60 wall (E/I facilities and refuge) Iv-Oil & Gas www.iv-groep.nl
  • 23. PROJECT MANAGEMENT ● ENGINEERING ● CONTRACTING TOPSIDES ENERGY 2400 watt energy consumption (unmanned mode) Renewable energy sources (wind turbines and solar) WEIGHT Topsides : 340 tonnes Substructure : 860 tonnes Total : 1200 tonnes Iv-Oil & Gas www.iv-groep.nl
  • 24. PROJECT MANAGEMENT ● ENGINEERING ● CONTRACTING FABRICATION, TRANSPORT AND INSTALLATION Iv-Oil & Gas www.iv-groep.nl
  • 25. PROJECT MANAGEMENT ● ENGINEERING ● CONTRACTING FABRICATION, TRANSPORT AND INSTALLATION FABRICATION Fabrication at a facility which has unrestricted access to the North Sea. Delivery of mono column (rolled and pre-welded) Delivery of suction piles Fabrication substructure Integration of suction piles with the substructure Installation of sacrificial anodes Installation of SW pump, J-tube and riser inside column Iv-Oil & Gas www.iv-groep.nl
  • 26. PROJECT MANAGEMENT ● ENGINEERING ● CONTRACTING FABRICATION, TRANSPORT AND INSTALLATION TRANSPORT AND INSTALLATION Marine spread : Main tow tug 60-80 TBP Assisting tug 40 TBP Barge 300 – 400 ft Strand jacks (4 x 600 ton) Suction pumps (3 x) Hang-off frame (at stern of barge) Mooring winches (4 x allows for accurate manoeuvring) ROV spread (seabed survey and wellhead inspection) Survey & positioning spread (platform position monitoring) Iv-Oil & Gas www.iv-groep.nl
  • 27. PROJECT MANAGEMENT ● ENGINEERING ● CONTRACTING FABRICATION, TRANSPORT AND INSTALLATION INSTALLATION OPTIONS Topside pre-installed at top of column, transport with barge SIP3, offshore lowered with strand jacks (1x jacking), Topside pre-installed at lower section of column, transport with barge SIP3, substructure lowered offshore using strand jacks, deck lifted with strand jacks (2x jacking), Topside installed at top of column, transport on barge, offshore single lift HLV/SSCV (1x lifting), Topside on barge, substructure on barge, offshore installation deck with sheerleg/HLV/SSCV (2x lifting), Transport topside on barge, substructure in hooks sheerleg (1x lowering, 1x lifting). Iv-Oil & Gas www.iv-groep.nl
  • 28. PROJECT MANAGEMENT ● ENGINEERING ● CONTRACTING FABRICATION, TRANSPORT AND INSTALLATION INSTALLATION The installation of the platform consists of the following phases: Preparation phase Barge mooring Platform lowering Foundation installation Completion activities Iv-Oil & Gas www.iv-groep.nl
  • 29. PROJECT MANAGEMENT ● ENGINEERING ● CONTRACTING FABRICATION, TRANSPORT AND INSTALLATION INSTALLATION Sea fastening of substructure to the barge using hydraulic pins for swift release of the substructure from the barge after mooring, Tow to the field using tugs, Transport positive range of stability more than 50 degrees (criterion > 36 degrees), Lowering stability (hydrostatic and hydrodynamic) provided by ballast on the suction piles, Lowering and lifting systems using strand jacks, Suction pumps for the installation and future removal of the suction pile foundation, No divers required for installation and removal of installation equipment. Iv-Oil & Gas www.iv-groep.nl
  • 30. PROJECT MANAGEMENT ● ENGINEERING ● CONTRACTING SCHEDULE Iv-Oil & Gas www.iv-groep.nl
  • 31. PROJECT MANAGEMENT ● ENGINEERING ● CONTRACTING SCHEDULE DEFINITION OF PROJECT PHASES Conceptual design Detail design Procurement Construction Onshore test/commissioning Transportation and installation Iv-Oil & Gas www.iv-groep.nl
  • 32. PROJECT MANAGEMENT ● ENGINEERING ● CONTRACTING SCHEDULE CONCEPT PLANNING Iv-Oil & Gas www.iv-groep.nl
  • 33. PROJECT MANAGEMENT ● ENGINEERING ● CONTRACTING COST ESTIMATE Iv-Oil & Gas www.iv-groep.nl
  • 34. PROJECT MANAGEMENT ● ENGINEERING ● CONTRACTING COST ESTIMATE OVERVIEW Iv-Oil & Gas www.iv-groep.nl --- --- --- --- Grand Total           --- ---     Overall contingency ~15% --- ---     Certification --- ---     Insurance --- ---     Fabrication and installation --- ---     Design & Procurement --- --- --- --- Equipment (incl commisioning) ---   --- --- Helideck ---   --- --- Topsides structual steel ---   --- --- Substructure (€·10 3 ) (€·10 3 ) (€·10 3 ) (€·10 3 )     costs costs Total Other Fabrication FoB Description
  • 35. PROJECT MANAGEMENT ● ENGINEERING ● CONTRACTING END OF PRESENTATION QUESTIONS? Iv-Oil & Gas www.iv-groep.nl