Here's an update on the progress at the new cancer facility in Kearney, Nebraska. As you can see from the photo, the building is taking shape, and upcoming work being done at the site includes the following: -Installing the curtain wall glass on both the north and south sides of the building. -Paving the south parking lot. -Setting and connecting the air handling units by the end of the month. Upcoming work in August and September includes: -Installation of the CT and linear accelerator (LINAC) equipment in late August. -Starting the landscaping and build-out of the healing garden in September. The cancer center is targeted to open late this year.

  • No alternative text description for this image

We can't wait for the first patients to walk through the doors later this year.